Integrity Express Logistics Office Building
Blue Ash, OH Ben Hur installed 176 architectural precast panels using a 80 ton crawler crane on a structural steel frame....
read moreWorldwide Technology – New Corporate HQ
Maryland Heights, MO Ben Hur Construction and Steel Worx were contracted to fabricate and install 1,700 tons of structural steel for the new 200,000 square foot WWT Corporate HQ located in Westport Plaza. Ben Hur Construction also installed 587 pieces of precast for the new 204,000 square, four level new parking ramp located next to the new office...
read moreSinclair Building 14 Addition
Dayton, OH Ben Hur was contracted to erect 88 pieces of Architectural Precast on a steel frame building, of which 24 pieces were in and under the structure....