Scottish Rite Garage
St. Louis, MO Four story parking structure with 500 structural precast pieces and 55 architectural precast...
read moreMason Ridge Parking Garage
St. Louis, MO Erection of 307 piece precast concrete parking garage for a one level parking deck for existing medical...
read moreKingslanding Parking Garage
St. Louis, MO Erection of a four story parking garage for service to a new apartment complex, comprised of 344 precast concrete...
read moreBoulevard Parking Garage
St. Louis, MO Erection of a 4 level precast concrete parking structure comprised of 571 structural precast concrete...
read moreBi-State Parking Garage
St. Louis, MO Precast Erection of a two story parking structure comprised of 415 structural precast concrete sections. ...
read moreProctor and Gamble – Innovation Center
Cincinnati, OH This project required the erection of 1,530 tons of structural steel and 293,000 sq. ft. of composite floor...
read moreMaster Card Operations Center
O’Fallon, MO This projected consisted of the construction of a new 456,000 sq foot facility requiring the erection of 2,800 tons of structural steel and miscellaneous...
read moreAG Edwards – Building “F”
St. Louis, MO Ben Hur performed the erection of over 7,500 tons of structural steel and miscellaneous metals for this new 1,000,000 sq foot office...
read moreExcel Imaging CT Scanner Removal
St. Louis, MO This particular CT scanner was the first one ever installed by Ben Hur construction. Following the removal, Ben Hur performed the installation of the new, state-of-the-art 64 slice CT apparatus the following...
read moreBarnes-Jewish Christian West County MRI Removal
St. Louis, MO Removal of 17,000 pound MRI magnet. This same magnet was previously installed by Ben Hur Construction in...
read more